Task Date Complete
Project Proposal October 17, 2013
Project Plan Document Version 1.0 October 17, 2013
Skeleton Website October 17, 2013
Project Support Environment October 22, 2013
Requirements Document Version 1.0 October 31, 2013
Design Document Version 1.0 December 2, 2013
Iteration 1 December 2, 2013
Iteration 2 January 31, 2014
Faculty Presentation February 4, 2014
Iteration 3 March 4, 2014
SRS Abstract Submission Due March 20, 2014
Abstract Deadline NTASC March 24, 2014
SRS Electronic Poster Submission Due April 3 2014
Student Research Symposium Poster Due April 3 2014
NTASC April 5, 2014
Student Research Symposium Poster April 11, 2014
Iteration 4 April 18, 2014
User Manual Version 1.0 April 23, 2014
Developer Manual Version 1.0 April 23, 2014
System Integration and User Acceptance Testing April 29, 2014
Final Presentation May 1, 2014
Complete All Documents May 2, 2014
Final Product DVD May 5, 2014


Weekly Schedule
Time Monday Tuesday Wednesday Thursday Friday Saturday Sunday
8:00-9:00 a.m.              
9:00-10:00 a.m              
10:00-11:00 a.m              
11:00-12:00 p.m              
12:00-1:00 p.m Lunch
1:00-2:00 p.m              
2:00-3:00 p.m   Meeting @ TUC 330   Meeting @ TUC 330    
3:00-4:00 p.m   Meeting @ TUC 330      
4:00-5:00 p.m        
5:00-6:00 p.m Dinner
6:00-7:00 p.m Backup Meeting
@ TUC 330
         
7:00-8:00 p.m            
8:00-9:00 p.m