W.A.R.s


April 27, 2013 - May 4, 2013

Task Team Status Estimated Actual Comments
Presentation Preperation Greg, Alex, Baer Complete 5 5 Finalized our last presentation.
Android Development Alex Complete 5 6 Bug Fixes.

April 19, 2013 - April 26, 2013

Task Team Status Estimated Actual Comments
Documentation Greg In Progress 5 5 Worked on iPhone app User Manual.
iOS Developement Greg Complete 5 5 Implemented Dr. Lee's changes to text.
Android Development Alex Complete 5 6 Implementing Dr. Lee's changes to Weight Management and Other text.
CMS Baer Complete 4 4 Bug fixes and added links to apps on main page.

April 11, 2013 - April 18, 2013

Task Team Status Estimated Actual Comments
Documentation Greg In Progress 5 5 Worked on iphone app user manual.
Android Development Alex In Progress 5 6 Working on Weight Management.
Documentation Baer In Progress 4 4 Worked on survey section of CMS User Manual.
CMS Baer In Progress 4 4 Worked on Data Export section of CMS.

April 3, 2013 - April 10, 2013

Task Team Status Estimated Actual Comments
Android Web Connectivity Greg In Progress 5 5 Adding weight management web calls for android.
iPhone app Greg In Progress 5 5 Bug Fixes.
Android Development Alex Complete 5 6 Bug fixes.
Android Development Alex In Progress 5 6 Worked on Weight Management.
CMS Baer In Progress 4 4 Worked on CMS User Manual.
CMS Baer In Progress 4 4 Worked on CMS User Analytics.

March 26, 2013 - April 2, 2013

Task Team Status Estimated Actual Comments
Iphone Development Greg In Progress 5 5 Worked on Fort Worth Resources.
Iphone Development Greg In Progress 5 5 Worked on Iphone views.
User manual Greg In Progress 5 5 Began working on the user manual.
Android Development Alex Complete 5 6 Added Community Poll Section.
Android Development Alex Complete 5 6 Worked on Survey Navigation.
Android Development Alex Complete 8 9 Created Working links to be used for the resources views.
CMS Baer Complete 5 5 Added User Analytics to CMS.
CMS Baer In Progress 4 4 Worked on CMS Dashboard.

March 18, 2013 - March 25, 2013

Task Team Status Estimated Actual Comments
Iphone Development Greg In Progress 5 5 Worked on Surveys.
Iphone Development Greg Complete 5 5 Bug Fixes.
Android Development Alex Complete 4 4 Added health assessment scoring.
Android Development Alex Complete 6 6 Added Track and Poll section.
SRS Abstract Baer Complete 2 2 Completed the SRS Abstract
CMS Baer Complete 5 5 Added Fort Worth Resources.

March 10, 2013 - March 17, 2013

Task Team Status Estimated Actual Comments
Iphone Development Greg In Progress 5 5 Worked on iOS development.
Android Development Alex In Progress 5 6 Worked on Surveys. Added methods to create button grouping.
CMS Baer In Progress 6 7 Worked on Content Management System

March 2, 2013 - March 9, 2013

Task Team Status Estimated Actual Comments
Iphone Development Greg Complete 5 5 Surveys Work. Added Overview
Android Development Alex In Progress 5 6 App pulls surveys from database. Began working on assements.
Database Baer Complete 6 7 Updated Schema.

February 22, 2013 - March 1, 2013

Task Team Status Estimated Actual Comments
Content Management System Baer Complete 10 7 CreateUserAccount now responds with account information.
Android Development Alex In Progress 3 3 Working on password confirmation and comboboxes.
Android and Webservice communication Greg In Progress 2 2 Creating classes to communicate with the webservice.

February 14, 2013 - February 21, 2013

Task Team Status Estimated Actual Comments
Content Management System Baer Complete 10 7 Updated track and progress and community vote & poll sections.
Android Development Alex Complete 3 3 Updated account creation views to reflect changes in ios.
Diagrams Greg Complete 5 5 Updated iOS sequence diagrams.

February 6, 2013 - February 13, 2013

Task Team Status Estimated Actual Comments
Software Requirements Specification Alex Complete 2 2 Updated SRS to version 2.0.
iOS Development Greg In Progress 10 10 Updates to user creation (new wizard format), using new API methods, added community poll and track & progress sections, and added in-app web browser for resources.
Content Management System Baer In Progress 10 10 Added new methods to CMS API, added ability to edit user accounts, modified authentication, added ability to edit questions, and added ability to create survey responses.

January 30, 2013 - February 5, 2013

Task Team Status Estimated Actual Comments
Content Management System Baer In Progress 10 7 Built menu, improved the creation of health assessments, added ability to rename surveys, and create survey questions.
Android Documentation Alex Complete 3 3 Sequence and class diagrams for Android mobile application.
Iteration 2 Presentation All Complete 5 5

January 23, 2013 - January 29, 2013

Task Team Status Estimated Actual Comments
iOS development Greg In Progress 15 15 Questions and build custom radio buttons.
Android Development Alex In Progress 7 9 Learning Android development, sliding menu, and UI.
CMS Baer In Progress 5 4 User management and health assessment section management.
Website Baer Complete 2 2 W.A.R.s and some minor changes.
Iteration 2 Presentation All In Progress 2 2 Began work on iteration 2 presentation to be on January 31, 2013.
Documentation All In Progress 2 2 Began work updating documentation to reflect the state of the project at the end of iteration 2.

January 15, 2013 - January 22, 2013

Task Team Status Estimated Actual Comments
iOS development Greg In Progress 6 6 Working on displaying questions pulled from server.
Android Development Alex In Progress 5 6 Worked on Main page and learning Android development.
CMS & Database Baer Complete 5 4 Worked on communication between the CMS and Database
Website Baer Complete 2 2 Added deliverables.

December 5, 2012 - December 11, 2012

Task Team Status Estimated Actual Comments
Presentation All Completed 4 4 Prepared final presentation for HealthyFROGS project.
iOS Application Greg In Progress 2 2 Worked on layout and functionality.
Sequence Diagrams Baer, Greg Complete 2 2 Created diagrams for database and iOS application.

November 28, 2012 - December 04, 2012

Task Team Status Estimated Actual Comments
Web Service Baer In Progress 5 5 Worked on Web Service development.
Design Document Alex In Progress 3 3 Added to Design Document.
iOS Development Greg In Progress 8 8 Worked on the iOS application.

November 14, 2012 - November 20, 2012

Task Team Status Estimated Actual Comments
iOS App Greg In Progress 10 10 Building UI mockups and initial parts of iOS app.
Design Document All In Progress 3 3 Introduction and design constraints.
Updated HeatlhyFROG's website wars Baer Complete .5 .5 Added the latest WAR to the website.
Team Meeting All Success 2 2 Covered system design and interface for web service.
Web Service Alex, Baer, Daniel In Progress 5 5 Started implementation of web service.

November 7, 2012 - November 13, 2012

Task Team Status Estimated Actual Comments
Software Requirements Specification All In Progress 3 2 Working on SRS revision.
Database Schema Greg, Baer, Daniel Complete 3 3 Met on Saturday to work on database schema.
Updated HeatlhyFROG's website wars Alex Complete 1 1 Uploaded the latest WAR to the website.
Application prototype Greg In Progress 2 1 Continued work on app prototype.
Geocode Prototype Daniel In Progress 6 6 Developed a preliminary Geocode prototype.
Design Document Alex, Baer In Progress 3 2 Began working on design Document version 1.

October 31, 2012 - November 6, 2012

Task Team Status Estimated Actual Comments
Software Requirements Specification version 1.2 All In Progress 6 5 Working on SRS version 1.2.
Setup Tortoise SVN on Senior Design Lab workstations. Alex, Baer Complete 1 1 Moved documents from www.box.com to Tortoise SVN.
Updated HeatlhyFROG's website wars Alex Complete 1 1 Uploaded the latest WAR to the website.
Transferred website to Tortoise SVN Baer Complete 2 1 Uploaded the website to Tortoise SVN.
Application Prototype Greg In Progress 4 3 Developing GoodNEWS prototype.

October 24, 2012 - October 30, 2012

Task Team Status Estimated Actual Comments
Software Requirements Specification Version 1.1 All Complete 4 4 Completed our SRS version 1.1
Client Meeting All Complete 1 1 Met with clients on October 24, 2012 to continue gathering requirements for project.
Design Document All In Progress 1 1 Set up outline for design doc.
Website Baer Complete .5 .5 Added W.A.R. for the week, and fixed problems with the media page.
Resource Acquisition Baer Complete .5 .5 Outlined steps for clients to obtain developer accounts, hosting, domain names, etc. required for the project.
Use Case Models Alex Complete 2 2 Completed use case models to be used in Software Requirements Specification and Design Document.

October 17, 2012 - October 23, 2012

Task Team Status Estimated Actual Comments
Software Requirements Specification version 1 All Complete 5 5 Completed our SRS version 1.
Meeting with GoodNEWS team Alex, Baer, Greg Complete 1 1.5 Met with the GoodNEWS team to discuss requirements.
Updated HeatlhyFROG's website team pictures Alex Complete .5 .5 Uploaded the website with pictures from the meeting.
Updated HeatlhyFROG's website wars Alex, Baer Complete 1 1 Uploaded the website with latest WAR and restructured the order of the WARs.

October 10, 2012 - October 16, 2012

Task Team Status Estimated Actual Comments
Group Member Bio All In Progress .5 .5 Created team bio.
Updated Website Alex Complete 1 1 Updated website with HealthyFROGS' bio information.
User Interface Greg In Progress 5 5 UI still being designed.
Project Support Environment All Complete 1 1 The necessary software has been installed on the HealthyFROGS' Senior Design Lab work stations.
Project Plan Revision Baer Complete 1 1 Project Plan 1.1 revision complete.
Group Assessments All Complete .5 .5 Group Assessments completed.
Website Overview All In Progress .5 .5 Website Overview revised.
Rough Requirements All In Progress 4 4 Initial draft of Software Specifications document created.
Website Overview Alex Complete .5 .5 Shortened the Project Overview on the HealthyFROGS' website.

October 3, 2012 - October 9, 2012

Task Team Status Estimated Actual Comments
Project Plan All Complete 5 4 Completed our project plan.
Website Baer Complete 4 4 Transferred the website over to brazos.cs.tcu server.
User Interface Greg In Progress 3 2 Still constructing potential UI models.

September 25, 2012 - October 2, 2012

Task Team Status Estimated Actual Comments
Project Proposal All Complete 2 1.5 Completed our project proposal.
Website Baer In Progress 4 4 Created a website to begin uploading our documentation to.
Project Plan All In Progress 5 4 Began working on project plan.
Logo Creation Baer, Daniel In Progress 1 1 Still trying to come up with new logo ideas.
Gantt Chart Alex, Baer Complete 1 1 Created the Gantt Chart for HealthyFROGS.
User Interface Greg In Progress 1 .5 Currently developing several different possible user interfaces for the GoodNEWS group to look at.
Client Meeting All Complete 1 1 Met with the client for the first time and discussed the client's needs for a multiplatform mobile application that deals with personal health.