Task | Duration | Start | Finish |
---|---|---|---|
Project Proposal | 3 Days | 2012-09-29 | 2012-10-02 |
Project Plan | 2 Days | 2012-10-02 | 2012-10-04 |
Project Support Environment | 7 Days | 2012-10-04 | 2012-10-11 |
Software Requirements Specification | 40 Days | 2012-10-14 | 2012-11-23 |
Design Document | 45 Days | 2012-10-22 | 2012-12-06 |
Iteration 1 | 30 Days | 2012-11-10 | 2012-12-10 |
Iteration 2 | 49 Days | 2012-11-27 | 2012-01-24 |
NTSAC Abstract | 7 Days | 2012-01-25 | 2012-02-01 |
Test Plan | 14 Days | 2013-01-22 | 2013-02-05 |
Iteration 3 | 28 Days | 2013-01-15 | 2013-02-19 |
Iteration 4 | 23 Days | 2013-02-12 | 2013-03-07 |
Acceptance Testing | 44 Days | 2013-02-12 | 2013-03-28 |
SRS Poster | 7 Days | 2013-04-05 | 2013-04-12 |
Developer Manual | 65 Days | 2013-02-12 | 2013-04-18 |
User Manual | 65 Days | 2013-02-12 | 2013-04-18 |
SRS | 1 Day | 2013-04-19 | 2013-04-19 |
Final DVD Submission | 1 Days | 2013-05-01 | 2013-05-02 |
Final Presentation | 1 Days | 2013-05-02 | 2013-05-02 |