Schedule


Task Duration Start Finish
Project Proposal 3 Days 2012-09-29 2012-10-02
Project Plan 2 Days 2012-10-02 2012-10-04
Project Support Environment 7 Days 2012-10-04 2012-10-11
Software Requirements Specification 40 Days 2012-10-14 2012-11-23
Design Document 45 Days 2012-10-22 2012-12-06
Iteration 1 30 Days 2012-11-10 2012-12-10
Iteration 2 49 Days 2012-11-27 2012-01-24
NTSAC Abstract 7 Days 2012-01-25 2012-02-01
Test Plan 14 Days 2013-01-22 2013-02-05
Iteration 3 28 Days 2013-01-15 2013-02-19
Iteration 4 23 Days 2013-02-12 2013-03-07
Acceptance Testing 44 Days 2013-02-12 2013-03-28
SRS Poster 7 Days 2013-04-05 2013-04-12
Developer Manual 65 Days 2013-02-12 2013-04-18
User Manual 65 Days 2013-02-12 2013-04-18
SRS 1 Day 2013-04-19 2013-04-19
Final DVD Submission 1 Days 2013-05-01 2013-05-02
Final Presentation 1 Days 2013-05-02 2013-05-02