Schedule
Click here for a Gantt Chart
| ID | Task Name | Duration | Start | Finish |
| 1 | Project Proposal | 5 days | 10/9/2009 | 10/15/2009 |
| 2 | Project Support Environment 1 | 33 days | 9/1/2009 | 10/15/2009 |
| 3 | Background Research | 72 days | 9/1/2009 | 12/8/2010 |
| 4 | Project Plan v1.0 | 4 days | 10/16/2009 | 10/20/2009 |
| 5 | Software Requirements Specification v1.0 | 9 days | 10/21/2009 | 11/1/2009 |
| 6 | Design Documentation V1.0 | 16 days | 11/9/2009 | 11/30/2009 |
| 7 | Iteration 1 (GUI, Filtering, SPOTs) | 21 days | 11/16/2009 | 12/14/2009 |
| 8 | Iteration 2 (Training) | 39 days | 12/15/2009 | 2/2/2010 |
| 9 | Iteration 3 (Recognition) | 21 days | 2/3/2010 | 3/1/2010 |
| 10 | Iteration 4 (Demo) | 35 days | 3/3/2010 | 4/16/2010 |
| 11 | Acceptance Testing | 60 days | 2/11/2010 | 4/29/2010 |
| 12 | Test Plan | 41 days | 2/25/2010 | 4/19/2010 |
| 13 | Developer's Guide | 82 days | 1/15/2010 | 4/29/2010 |
| 14 | User Manual | 81 days | 1/15/2010 | 4/28/2010 |
| 15 | SRS Poster | 5 days | 4/12/2010 | 4/16/2010 |
| 16 | Final Presentation | 15 days | 4/12/2010 | 4/30/2010 |
| 17 | Final Project DVD | 6 days | 4/26/2010 | 5/3/2010 |