WARs

Weekly Activities Reports

Week 27, 25th Apr - 30th Apr, 2016

Task Team Member Time Estimated Time Taken Status Comments
Bug Fixes and Desktop App Sam Kent 30 hours 30 hours Complete Testing and Results part on the web app
User Manual and Final Presentation Nathan Johnson 20 hours 20 hours Complete Finishing user manual and editing videos and finalizaing presentation
Web App and final testing Aakash Tyagi 29 hours 29 hours Complete Final touches in web app and system testing
Web App and Documents Jack Kempner 29 hours 29 hours Complete Testing web app and revising documents

Week 26, 18th Apr - 24th Apr, 2016

Task Team Member Time Estimated Time Taken Status Comments
Final Bug Fixes Sam Kent 12 hours 20 hours Complete Cleaning up any stray bugs in the desktop application
Completing User Manual Nathan Johnson 8 hours 8 hours Complete Finalizing content for user manual and formatting
Website Final Touches Aakash Tyagi 8 hours 20 hours Complete Editting UI to be more user friendly and fixing bug fixes
Application Testing Jack Kempner 15 hours 20 hours Complete Creating and using test cases for the Complete application

Week 25, 11th Apr - 17th Apr, 2016

Task Team Member Time Estimated Time Taken Status Comments
Creating Presentation Sam Kent 8 hours ~8 hours Complete Preparing the presentation for North Texas
Editting Presentation Nathan Johnson 4 hours ~4 hours Complete Ensuring formatting is uniform
Prepping for Presentation Aakash Tyagi 4 hours ~4 hours Complete
Prepping for Presentation Jack Kempner 4 hours ~4 hours Complete

Week 24, 4th Apr - 10th Apr, 2016

Task Team Member Time Estimated Time Taken Status Comments
Bug fixes Sam Kent 10 hours ~15 hours Incomplete Chasing a bug that causes the .gbd file to not show up the first time it is downloaded
Syncing Results Nathan Johnson 10 hours ~10 hours Incomplete Linking the application results with the website results
Web application Aakash Tyagi 8 hours ~10 hours Complete Bug fixes regarding user accounts
Web Application Jack Kempner 8 hours ~8 hours Incomplete Polishing the front-end

Week 23, 28th Mar - 3rd Apr, 2016

Task Team Member Time Estimated Time Taken Status Comments
Making Results screen Sam Kent 10 hours ~15 hours Complete Getting the desktop application to display results
SRS Poster Nathan Johnson 8 hours ~10 hours Complete Dealing with formatting errors and content issues
Web application Aakash Tyagi 15 hours ~15 hours Complete Getting results to display on the web application
Web Application Jack Kempner 8 hours ~8 hours Incomplete Making the front-end

Week 22, 21th Mar - 27th Mar, 2016

Task Team Member Time Estimated Time Taken Status Comments
Generating Results Sam Kent 6 hours ~10 hours Complete Getting the Kinect to accurately generate exercise results
Researching Nathan Johnson 10 hours ~20 hours Complete Determining what sort of graphing technology to use
Web application Aakash Tyagi 10 hours ~10 hours Incomplete Getting assigned sessions to work
Web Application Jack Kempner 8 hours ~8 hours Incomplete Making the front-end

Week 21, 14th Mar - 20th Mar, 2016

Task Team Member Time Estimated Time Taken Status Comments
Generating Results Sam Kent 6 hours ~12 hours Incomplete Getting the Kinect to accurately generate exercise results
Downloading GBDs Nathan Johnson 15 hours ~3 hours Complete Getting .gbd files from the website
Web application Aakash Tyagi 10 hours ~10 hours Incomplete Getting assigned sessions to work
Web Application Jack Kempner 8 hours ~8 hours Incomplete Making the front-end

Week 20, 7th Mar - 13th Mar, 2016

Task Team Member Time Estimated Time Taken Status Comments
Database Link Sam Kent 10 hours ~10 hours Complete Researching server side SQL scripts
Database Link Nathan Johnson 12 hours ~6 hours Complete Linking the website with the application
Web application Aakash Tyagi 7 hours ~7 hours Complete Creating file upload
Database Jack Kempner 8 hours ~8 hours Complete Developing .gbd storage

Week 19, 29th Feb - 6th Mar, 2016

Task Team Member Time Estimated Time Taken Status Comments
Database Link Sam Kent 10 hours ~10 hours Incomplete Researching server side SQL scripts
Database Link Nathan Johnson 12 hours ~15 hours Incomplete Linking the website with the application
Web application Aakash Tyagi 7 hours ~7 hours Incomplete Creating file upload
Database Jack Kempner 8 hours ~8 hours Incomplete Developing .gbd storage

Week 18, 22nd Feb - 28th Feb, 2016

Task Team Member Time Estimated Time Taken Status Comments
Database Link Sam Kent 10 hours ~10 hours Incomplete Researching server side SQL scripts
Database Link Nathan Johnson 12 hours ~10 hours Incomplete Linking the website with the application
Web application Aakash Tyagi 7 hours ~7 hours Incomplete Researching server side database scripts
Database Jack Kempner 8 hours ~8 hours Incomplete Developing .gbd storage

Week 17, 15th Feb - 21st Feb, 2016

Task Team Member Time Estimated Time Taken Status Comments
Developing Session Architecture Sam Kent 10 hours ~10 hours Complete Getting the app to accept session files
Database Link Nathan Johnson 6 hours ~12 hours Incomplete Linking the website with the application
Web application Aakash Tyagi 7 hours ~7 hours Incomplete Researching server side SQL scripts
Database Jack Kempner 8 hours ~8 hours Incomplete Developing .gbd storage

Week 16, 7th Feb - 14th Feb, 2016

Task Team Member Time Estimated Time Taken Status Comments
Developing Session Architecture Sam Kent 6 hours ~8 hours Incomplete Getting the app to accept session files
Unity Frontend Nathan Johnson 10 hours ~10 hours Complete Finishing UI
Web application Aakash Tyagi 8 hours ~8 hours Complete Developing accounts
Web application Jack Kempner 6 hours ~6 hours Complete Completing front-end

Week 15, 31st Jan - 6th Feb, 2016

Task Team Member Time Estimated Time Taken Status Comments
Working on gesture recognition Sam Kent 8 hours ~10 hours Complete Increasing the level of accuracy
Unity Frontend Nathan Johnson 6 hours ~10 hours Incomplete Finishing UI
Web Database Aakash Tyagi 7 hours ~7 hours Incomplete Working on classes
Web application Jack Kempner 7 hours ~7 hours Incomplete Completing front-end

Week 14, 24th - 30th Jan, 2016

Task Team Member Time Estimated Time Taken Status Comments
Working on Presentation All team members 6 hours ~7 hours Complete Polishing and updating presentation
Finishing Iteration II All team members 12 hours ~12 hours Incomplete Bug fixes, UI polish

Week 13, 17th - 23th Jan, 2016

Task Team Member Time Estimated Time Taken Status Comments
Working on Kinect integration Sam Kent 8 hours ~10 hours Complete Implementing the Kinect in Unity
Unity backend Nathan Johnson 6 hours ~5 hours Complete Fixing the unity bugs
Web application Aakash Tyagi 7 hours ~8 hours Incomplete Completing back-end
Web application Jack Kempner 7 hours ~7 hours Incomplete Completing front-end

Week 12, 10th - 16th Jan, 2016

Task Team Member Time Estimated Time Taken Status Comments
Completing Kinect Back-end Sam Kent 8 hours ~8 hours Incomplete Implementing unity backend
Unity GUI Nathan Johnson 6 hours ~4 hours Incomplete Design and implementation
Web application Aakash Tyagi 7 hours ~7 hours Incomplete Completing front-end
Web application Jack Kempner 7 hours ~7 hours Incomplete Establishing back-end database link

Winter Break

Task Team Member Time Estimated Time Taken Status Comments
Unity Research Sam Kent & Nathan Johnson 20 hours ~20 hours Complete GUI and determining the necessary 3D models
Working on the web application Aakash Tyagi & Jack Kempner 10 hours ~10 hours Complete Setting up front-end

Week 11, 13th - 19th Dec, 2015

Task Team Member Time Estimated Time Taken Status Comments
Presentation All 10 hours ~10 hours Complete Brushing up the presentation

Week 10, 6th - 12th Dec, 2015

Task Team Member Time Estimated Time Taken Status Comments
Presentation Sam Kent 6 hours ~6 hours Complete Kinect and Gesture builder
Presentations Nathan Johnson 5 hours ~5 hours Complete ER models and database relations
Presentation Aakash Tyagi 8 hours ~8 hours Complete Web App and compiling the complete presentation
Presentation Jack Kempner 7 hours ~7 hours Complete Prototypes, project overview and requirements

Week 9, 29th Nov - 5th Dec, 2015

Task Team Member Time Estimated Time Taken Status Comments
Kinect App and Unity Sam Kent 7 hours ~6 hours Complete Integrating Unity with Kinect
Design document and Database Implementation Nathan Johnson 7 hours ~7 hours Complete Database implementation with Web App
Design document and Web app Aakash Tyagi 8 hours ~7 hours Complete Design Document completion and web app implementation
Sequence diagrams and design document Jack Kempner 7 hours ~8 hours Complete Revising the sequence diagrams and design document

Week 8, 22nd - 28th Nov, 2015

Task Team Member Time Estimated Time Taken Status Comments
Design document and Unity Sam Kent 6 hours ~6 hours Complete Class diagrams and kinect app
Design document and ER models Nathan Johnson 7 hours ~7 hours Complete Improving ER diagram and database models
Design document Aakash Tyagi 8 hours ~7 hours Complete State diagrams and completing design document
Sequence diagrams and use cases Jack Kempner 7 hours ~8 hours Complete Improved sequence diagrams and use cases + prototypes for design document

Week 7, 15th - 21st Nov, 2015

Task Team Member Time Estimated Time Taken Status Comments
Unity integration and design document Sam Kent 7 hours ~9 hours Complete Researching unity integration with Kinect app and working on design document
Unity integration, design document and ER models Nathan Johnson 8 hours 9 hours Complete Researching unity integration with Kinect app, working on design document and describing ER models in detail
Unity integration, design document and web app Aakash Tyagi 8 hours ~9 hours Complete Researching unity integration with Kinect app, working on design document and working on finishing the protype requirements of web app
Sequence diagrams Jack Kempner 8 hours 9 hours Complete Sequence diagrams for design document

Week 6, 8th - 14th Nov, 2015

Task Team Member Time Estimated Time Taken Status Comments
Continuous gestures and requirements document Sam Kent 7 hours 8 hours Complete Researching gesture recognition in Kinect app and requirements document
Prototype diagrams Jack Kempner 8 hours ~8 hours Complete Prototyping for requirements documents
Prototype diagrams and use cases Nathan Johnson 7 hours ~8 hours Complete Prototyping and use cases for requirements documents
Use cases and requirements documents Aakash Tyagi 7 hours ~8 hours Complete Use cases for requirements documents and finishing up the document

Week 5, 1st - 7th Nov, 2015

Task Team Member Time Estimated Time Taken Status Comments
Prototype diagrams and continuous gestures Sam Kent 7 hours ~7 hours Complete Prototyping for requirements documents and gesture recognition in Kinect app
Prototype diagrams and database Nathan Johnson 7 hours ~8 hours Complete Prototyping for requirements documents and setting up database for Kinect web app
Prototype diagrams and use cases Jack Kempner 7 hours ~8 hours Complete Prototyping and use cases for requirements documents
Wars and Web UML Aakash Tyagi 6 hours ~6 hours Complete Updating WARs and designing Web UML diagrams

Week 4, 25th - 31st Oct, 2015

Task Team Member Time Estimated Time Taken Status Comments
Unity Research Jack Kempner 6 hours 6 hours Complete Motion and particle attachment in Unity
Web App Aakash Tyagi 7 hours ~7 hours Complete Setting up basic framework for Elemental Kinection Web App
Database Nathan Johnson 5 hours 5 hours Complete ER Models & setting up database
Kinect App Sam Kent 7 hours 8 hours Complete Testing different measurement techniques in exercises

Week 3, 18th - 24th Oct, 2015

Task Team Member Time Estimated Time Taken Status Comments
Documents Sam Kent 4 hours ~ 4 hours Complete Requirement Docs and Project Plan Revision
UML Diagrams Nathan Johnson, Jack Kempner 4 hours ~ 4 hours Complete UML Diagrams & use cases
System Architecture Aakash Tyagi 3 hours ~ 3 hours Complete System Architecture and updating the website

Week 2, 11th - 17th Oct, 2015

Task Team Member Time Estimated Time Taken Status Comments
Kinect Prototype Application Sam Kent, Jack Kempner, Aakash Tyagi 5 hours ~ 5 hours Complete A prototype application that counts reps and recognizes gestures
Bitbucket, Git, Visual Studio Sam Kent, Jack Kempner, Aakash Tyagi 1 hours ~ 2 hours Complete How to use git and bitbucket with Visual Studio 2015
Documents Nathan Johnson 3 hours ~ 4 hours Complete Project Plan v1.1

Week 1, 4th - 10th Oct, 2015

Task Team Member Time Estimated Time Taken Status Comments
Kinect Tutorials Sam Kent, Jack Kempner, Aakash Tyagi, Nathan Johnson 7 hours ~ 9 hours Complete Online Kinect tutorials from microsoft
Unity Research Sam Kent 3 hours ~ 3 hours Complete How to use unity API with Kinect
Documents Nathan Johnson 2 hours ~ 2 hours Complete Project Plan v1.0