Schedule
Task Completion Date
Skeleton Website 10 October 2014
Project Plan v1.0 19 October 2014
Requirements Document v1.0 26 October 2014
Design Documentation v1.0 09 December 2014
Iteration 1 - Basic Layout for Template Two 09 January 2015
Iteration 2 - Functioning Template Two 30 January 2015
TCU Faculty Presentation 03 February 2015
User Manual 27 February 2015
Iteration 3 - Functioning Templates One and Three 19 March 2015
SRS Abstract Submission 19 March 2015
NTASC Abstract Submission 31 March 2015
Iteration 4 - Revisions and Testing 01 April 2015
SRS Poster Submission 09 April 2015
Developers Guide 09 April 2015
SRS 17 April 2015
NTASC Wichita Falls 18 April 2015
Final Product 23 April 2015
Complete All Documents 23 April 2015
Final Presentation 30 April 2015