Schedule

Tentative schedule for project documents and deliverables.

Task Completion Date
Project Plan v1.0 17 October 2013
Skeleton Website 25 October 2013
Requirements Documentation v1.0 07 November 2013
Design Documentation v1.0 05 December 2013
Iteration 1 12 December 2013
Iteration 2 30 January 2014
TCU Faculty Presentation 04 February 2014
User Manual 20 February 2014
Developers Guide 20 February 2014
Iteration 3 28 February 2014
SRS Abstract Submission 20 March 2014
NTASC Abstract Submission 24 March 2014
Iteration 4 25 March 2014
SRS Poster Submission 03 April 2014
NTASC 05 April 2014
SRS 11 April 2014
Final Presentation 01 May 2014
Complete All Documents 02 May 2014
Final Product DVD 05 May 2014