W.A.R.s

April 14, 2013 - April 20, 2013

Task
Team
Status
Estimated
Actual
Comments
iOS iteration 3
Reid
In Progress
40
40/div>
Updated user manual, Cleaned up code, SRS Poster
Android iteration 3
Matt
In Progress
40
40
Updated user manual, Cleaned up code, SRS Poster
Web application iteration 3
Jose
In Progress
30
35
Updated user manual, State Diagram, SRS Poster

April 7, 2013 - April 13, 2013

Task
Team
Status
Estimated
Actual
Comments
iOS iteration 3
Reid
In Progress
40
40/div>
Updated user manual, NTASC presentation, Cleaned up code, SRS Poster
Android iteration 3
Matt
In Progress
40
40
Updated user manual, NTASC presentation, Cleaned up code, SRS Poster
Web application iteration 3
Jose
In Progress
30
35
Updated user manual, NTASC presentation, State Diagram, SRS Poster

March 31, 2013 - April 6, 2013

Task
Team
Status
Estimated
Actual
Comments
iOS iteration 3
Reid
In Progress
40
50
Updated user manual, continuing testing on application, working on NTASC presentation
Android iteration 3
Matt
In Progress
20
25
Updated user manual, continuing testing on application
Web application iteration 3
Jose
In Progress
30
35
Updated user manual, continuing testing of site, working on state diagram, SRS poster

March 24, 2013 - March 30, 2013

Task
Team
Status
Estimated
Actual
Comments
iOS iteration 3
Reid
In Progress
40
50
Updated user manual, continuing testing on application
Android iteration 3
Matt
In Progress
20
25
Updated user manual, continuing testing on application
Web application iteration 3
Jose
In Progress
30
35
Updated user manual, continuing testing of site, working on state diagram

March 17, 2013 - March 23, 2013

Task
Team
Status
Estimated
Actual
Comments
iOS iteration 3
Reid
In Progress
40
50
Android iteration 3
Matt
In Progress
20
25
Web application iteration 3
Jose
In Progress
30
25

March 10, 2013 - March 16, 2013

Task
Team
Status
Estimated
Actual
Comments
iOS iteration 3
Reid
In Progress
40
50
Iphone updates, career help screen, updated homescreen, photo editing, working client on feedback (google docs)
Android iteration 3
Matt
In Progress
20
25
Android version feedback, updated homescreen,working customer feedback from google docs.
Web application iteration 3
Jose
In Progress
30
25
Updating website per client feed back, updating Senior design website, working on customer feedback from google docs.

March 3, 2013 - March 9, 2013

Task
Team
Status
Estimated
Actual
Comments
iOS iteration 3
Reid
In Progress
40
50
Formatted checklist pages, edit reminders, waiting on customer feedback
Android iteration 3
Matt
In Progress
20
25
Updated homescreen, updated checklist, waiting on customer feedback
Web application iteration 3
Jose
In Progress
30
25
Updating website per client feed back, working on user manual

February 24, 2013 - March 2, 2013

Task
Team
Status
Estimated
Actual
Comments
iOS iteration 3
Reid
In Progress
40
50
Added internal checklist links, photo editing, waiting on customer feedback
Android iteration 3
Matt
In Progress
20
25
Adding links to checklist, reminders, and modifying look of home screen, based on customer feedbacktd>
Web application iteration 3
Jose
In Progress
30
25
Updating website per client feed back, waiting on customer feedback

February 17, 2013 - February 23, 2013

Task
Team
Status
Estimated
Actual
Comments
iOS iteration 3
Reid
In Progress
40
50
Browser features, visual updates per client. Error handling and bug fixes to application
Android iteration 3
Matt
In Progress
20
25
Adding links to checklist, reminders, and modifying look of home screen. Also adding search bar to the web views.
Web application iteration 3
Jose
In Progress
30
25
Updating website per client feed back, updating Senior design website.

February 10, 2013 - February 16, 2013

Task
Team
Status
Estimated
Actual
Comments
iOS iteration 3
Reid
In Progress
15
15
Custom check boxes, updated visual updated, per client. Changed the way profile creation worked.
Android iteration 3
Matt
In Progress
15
15
Made select grade mandatory, fixed color background. Modified options page, and checklist page. Worked on layout of all pages.
Web application iteration 3
Jose
In Progress
30
25
Responsive website, cleaner code, waiting on feedback

February 3, 2013 - February 9, 2013

Task
Team
Status
Estimated
Actual
Comments
iOS iteration 3
Reid
In Progress
40
50
Met with customer, provided feedback. Updating application per customer needs.
Android iteration 3
Matt
In Progress
20
25
Met with customer, worked with check boxes and issues with application and layout.
Web application iteration 3
Jose
In Progress
30
25
Updated senior design website, updated website per customer feedback. Waiting on content information.

January 27, 2013 - Februrary 2, 2013

Task
Team
Status
Estimated
Actual
Comments
iOS iteration 3
Reid
In Progress
40
50
Completed iPhone and iPad views, and completed the iOS code. Updated application per customer feedback
Android iteration 3
Matt
In Progress
20
25
created all the views, profile creation and error catching. Resolving issues with application and design
Web application iteration 3
Jose
In Progress
30
25
Updating per customer feedback. Updated documents on BullFrog website, and updated documentation

January 21, 2013 - January 26, 2013

Task
Team
Status
Estimated
Actual
Comments
iOS iteration 3
Reid
In Progress
40
50
Completed iPhone and iPad views, and completed the iOS code. Update application from customer feedback
Android iteration 3
Matt
In Progress
20
25
Created all the views, profile creation and error catching. Updating application from customer feedback
Web application iteration 2
Jose
Complete
30
25
Responsive website, cleaner code, waiting on feedback. Updating application from customer feedback

January 14, 2013 - January 20, 2013

Task
Team
Status
Estimated
Actual
Comments
iOS iteration 2
Reid
Complete
40
50
Completed iPhone and iPad views, and completed the iOS code. Need a device to test videos.
Android iteration 2
Matt
Complete
20
25
created all the views, profile creation and error catching
Web application iteration 2
Jose
In Progress
30
25
Responsive website, cleaner code, waiting on feedback

December 9, 2012 - December 15, 2012

Task
Team
Status
Estimated
Actual
Comments
Completed state diagram
Matt
Complete
4
4
Completed state diagram
Design Document v1.1
Reid, Matt
Complete
3
3
Completed design document
Presentation for Iteration 1
All
Complete
3
3
Completed Presentation
SVN updating
Reid
Complete
3
2
Updated SVN documents
BullFrog website update
Jose
Complete
2
2
Deliverables\Wars update

December 2, 2012 - December 8, 2012

Task
Team
Status
Estimated
Actual
Comments
Update website for TCC
Jose
In Progress
4
4
Updating website
Design Document v1.1
Reid, Matt
In Progress
3
3
Creating the design document
SVN updating
Reid
Complete
3
2
Updated SVN documents
BullFrog website update
Jose
Complete
2
2
Wars update

November 25, 2012 - December 1, 2012

Task
Team
Status
Estimated
Actual
Comments
Completed state diagram
Matt
Complete
4
4
Completed state diagram
Design Document v1.1
All
In Progress
3
3
Creating the design document
Create iPad views
All
In Progress
3
3
iPad view for iOS application
SVN updating
Reid
Complete
3
2
Updated SVN documents
BullFrog website update
Jose
Complete
2
2
Wars update

November 18, 2012 - November 23, 2012

Task
Team
Status
Estimated
Actual
Comments
Feedback on Mobile web application
All
Complete
1
1
TCC feedback meeting
Implementing TCC web application feedback
Jose,Reid
In progress
4
4
Need to research implementation techniques
BullFrog Website updating
Jose
In Progress
3
3
Updated BullFrog website
Converting documents to PDFs
Jose, Matt, Reid
Complete
2
2
Created documents
IOS application development
Reid
In Progress
2
2
Creating IOS application
Android application development
Avinash
In Progress
2
2
Creating Android application

November 11, 2012 - November 17, 2012

Task
Team
Status
Estimated
Actual
Comments
Advisory board meeting 
All
Complete
1
1
Attended board meeting
Design Document brainstorm
All
In Progress
2
2
Brainstorming the design document
Complete the mobile web application
Jose
Complete
4
4
Completed the web application
Web Application update
Jose, Reid
Complete
3
3
Updated the mobile web application from feedback
Requirements Document 1.1 complete
All
Complete
2
2
Completed RD 1.1
Wireframe Revision
Jose, Reid, Matt
Complete
2
2
Made revisions to the wireframe from client feedback

November 4 , 2012 - November 10, 2012

Task
Team
Status
Estimated
Actual
Comments
Software Requirements version 1.1
All
In Progress
6
5
Working on version 1.1
Setup Tortoise SVN on Senior Design Lab
Reid, Jose, Matt
Complete
1
1
Moved documents from www.google.com to Tortoise SVN.
Prototype for mobile web application
Jose
Complete
5
5
Creation of mobile web application
Creation of system architecture diagram
Jose
Complete
2
2
Created diagram for Requirements document
Completed Use Cases\Revisions
Reid, Matt
Complete
4
4
Uses cases completion
Android SDK installation
Avinash
Complete
2
2
Installed SDK and created a basic application

October 28, 2012 - November 3, 2012

Task
Team
Status
Estimated
Actual
Comments
Workstation update
All
Complete
1
1
Updated the workstations in the Lab
Client Meeting
All
Complete
1
1
Met with clients
Use cases discussion\creation
All
In Progress
3
3
Worked on use cases
Website updating
Jose
Complete
3
2
Updated the website
Requirements Document Revision
All
Complete
2
2
Updated the requirements document
Wireframe Revision
Jose, Reid, Matt
Complete
2
2
Made revisions to the wireframe from client feedback

October 21, 2012 - October 27, 2012

Task
Team
Status
Estimated
Actual
Comments
Software Requirements v1.0
All
Complete
5
5
Completed our version 1.
Meeting with TCC
Reid, Matt, Avinash
Complete
1
1
Met with the TCC Web Team to discuss requirements.
Apple Profile creation
Matt
Complete
.5
.5
Created a apple profile for development
Software Requirements Revision
All
Complete
2
1
Revised the requirements document
Wireframe creation
Jose
Complete
6
6
Wireframe creation
Questions to ask client discussion
All
Complete
1
1
Generated questions to ask client
Use cases discussion
All
In Progress
1
1
Discussion of use cases
Wireframe revision
Reid, Matt, Jose
Complete
2
2
Revised the wireframe

October 14, 2012 - October 20, 2012

Task
Team
Status
Estimated
Actual
Comments
Project Plan 1.0
All
Complete
1
1
Created Project Plan 1.0
Updated Website
Jose
Complete
2
2
Updated website with BullFrog Team members info
Requirements 1.0
All
In Progress
5
5
Nonfunctional and functional requirements
Workstation Support
All
Complete
1
1
The necessary software has been installed in Senior Design workstations.
Project Plan Revision
All
Complete
2
2
Project Plan 1.1 revision completed
Group Assessments
All
Complete
.5
.5
Group Assessments completed in lab
Website Overview Planning
All
In Progress
1
1
Website Overview