Schedule
Click Here to Download the GANTT Chart
Task Name: | Finish Date: |
Project Support Environment | 10/10/10 |
Project Plan Document | 10/31/10 |
Requirements Document | 11/16/10 |
Design Document | 11/30/10 |
Iteration#0 | 12/17/10 |
Iteration#1 | 01/18/11 |
Iteration#2 | 02/15/11 |
Test Plan (V 1.0) | 02/28/11 |
NTASC Abstract | 03/10/11 |
Iteration#3 | 03/22/11 |
Iteration#4 | 03/29/11 |
User Manual (V 1.0) | 03/29/11 |
Code Completion | 03/29/11 |
NTASC Presentation | 04/09/11 |
SRS Poster | 04/12/11 |
SRS |
04/15/11 |
Developer Guide | 04/20/11 |
Final Submission | 04/25/11 |
Final Presentation | 04/29/11 |